Thursday, June 24, 2010

Pizza oven #6


I have now achieved my first major milestone, I have a base on which to build the oven itself. I must be getting alittle more used to it but mixing, moving from the front of the house and pouring the slab seemed easier that the other concreting operations. I think the local hire man will be disappointed I'm finished. As you can see even more rebar to hold it together.

The slab has to cure for a few days so I can do some work on the front garden, it is looking truely tragic at the moment. I also need to start ordering the materials for the oven or there will be no building going on at all.

Friday, June 18, 2010

Pizza oven #5

It was a big day today, hired the concrete mixer and filled all of the blocks with concrete, only its called grout when its filling the blocks. It took about 1 cubic meter of concrete, which google tells me is 2.3 tonnes. I mixed it at the front, barrowed it up and around the back, and then put it in with a spade and a little funnel thing I came up with.


Next is to box up for the slab that goes on top, and which will hold up the pizza oven and BBQ, not too hard so should give a little time for the body to recover. I am feeling a little weary & sore tonight!

Tuesday, June 15, 2010

Pizza oven #4


The base for the pizza oven progresses. I am getting a bit better at block laying, but I'm sure I'm Auckland's slowest. The Magazine article author, Robin Overall, said that the blocks should just be laid on each other and then filled with concrete, it would be faster and more accurate for people who haven't laid block/bricks before and I'm sure he is right.

I decided to mortar the block together as i) I wanted to learn how and ii) as its 2m tall I wanted more strength while I am pouring the concrete into the blocks. I've added a bond beam, again due to it's height and the length of it.

Friday, June 11, 2010

Pizza oven #3


The rain stopped so I laid a few more blocks. Hopefully I will know how to lay blocks by the time I'm finished...

Pizza oven #2

It's raining today so I don't think I'll get much done.

I've been in touch with The Shed magazine about the article, you can call 09 302 3172 or email fiona@theshedmag.co.nz. They will send the article for NZ $10.00.

Thursday, June 10, 2010

Pizza Oven #1


Our family loves their home made pizzas so some time ago I decided to make a pizza oven. The inspiration came from a magazine article in the Shed Magazine, my next door neighbour got onto it straight away and built one so I have some motivation to do mine, and someone to ask advice if needed.

I decided to build it next to the deck at the back of the house, we had cleared some privets out of area some time ago and it was an obvious place to build it. However I decided to do a bit more, the pizza oven needs a base of about 1.4m by 1.4m and I had an area that was 2.2m long, so I decided to build the base 1.4m by 2.2m and have a pizza oven on one side and then a brick braai/BBQ on the other side.

That decided the first job was clearing the area for the footings. Unfortunately the area where to oven was to go had a number of privet and other stumps and the whole area was about 10cm deep in tree roots. Plastic and bark mulch had been laid down years before we moved in and was now a bed of roots. Digging was accomplished more with an axe than a spade but the footings were prepared. Probably spent too much time here but wanted to make sure the footings would be level.

The material for the base was ordered and delivered, but all the the front of the house and so began the task of carrying stuff round the back, 145 concrete blocks at 3 blocks per load... you can work it out, but it took all afternoon and still a few left. I then cut the steel reinforcing (rebar) for the footings and blocks.


Yesterday the weather was forecast to be fine so I hired a concrete mixer and set about pouring the footings, not too difficult a job, just hard work carrying numerous barrows of concrete from the mixer at the front of the house to the back, transferring into buckets to get down the steps and then into the footings. Put about 50mm of concrete in, then put in the rebar, and then finished pouring the concrete.

Once I had finished pouring the concrete, I waited for an hour (well a bit of tidying up, and a cup of tea produced by Alison) and then I laid the first course of blocks. Took a while to get them all level and square especially as I am trying to mortar them together but got there in the end.

Finally inserted the vertical rebar to go through the masonry blocks. It is going to be a challenge getting the blocks over the rebar, as the whole base will end up 2m high from the group in order to be at the right height next to the deck.

Firsts for the day: hiring a concrete mixer, mortaring and laying masonry blocks.

Home time



Vodafone had a reorganisation in the IT department and I took a redundancy package which means I am now at home, both looking for the next career opportunity, but also doing those projects at home that I have been thinking about for a while.

The first project was to create a paved area next to the driveway and a path to the steps to our front door. The front yard has been a tragic area for a while (years actually) ever since our house renovations. This has been done but the front lawn has to wait for a while as it is currently covered in builders mix for the next project... the Pizza oven.